8.3.2 - Correct testing sequence
Some tests will be carried out before the
supply is connected, whilst others cannot be performed until
the installation is energised. {Table 8.5} shows the correct
sequence of testing to reduce the possibility of accidents
to the minimum.
Table 8.5 - Correct sequence
for safe testing
|
BEFORE CONNECTION OF THE SUPPLY
|
1
|
Continuity of protective
conductors |
2
|
Main and supplementary
bonding continuity |
3
|
Continuity of ring final
circuit conductors |
4
|
Insulation resistance |
5
|
Site applied insulation |
6
|
Protection by separation |
7
|
Protection by barriers
and enclosures |
8
|
Insulation of non-conducting
floors and walls |
9
|
Polarity |
10
|
Earth electrode resistance
if an earth electrode resistance tester is used |
WITH THE SUPPLY CONNECTED
|
11
|
Earth electrode resistance
if an earth-fault loop tester or the ammeter and voltmeter
method are used |
12
|
Confirm correct polarity |
13
|
Earth-fault loop impedance |
14
|
Correct operation of
residual current devices |
15
|
Correct operation of
switches and isolators |
|