7.5.1 - Introduction
The electrical installation on a construction
site is there to provide lighting and power to enable the
work to proceed. By the very nature of the situation, the
installation will be subjected to the kind of ill treatment
which is unlikely to be applied to most fixed installations.
Those working on the site may be ankle deep in mud and thus
particularly susceptible to a shock to earth, and they may
be using portable tools such as drills and grinders in situations
where danger is more likely than in most factory situations.
The difficulty of ensuring that bonding requirements are
met on construction sites means that PME supplies must not
be used to supply them.
Installations will also, by definition,
he temporary. As the construction proceeds they will be
moved and altered. It is usual for such installations to
be subjected to thorough inspection and testing at intervals
which will never exceed three months. A formal visual inspection
of 110 V equipment should take place monthly; the effectiveness
of each RCD should be tested before every use by pressing
its test button.
As well as the erection of new buildings,
the requirements for construction sites will
also apply to:
1. - sites where repairs, alterations
or additions are carried out
2. - demolition of buildings
3. - public engineering works
4.
-civil engineering operations, such as road building,
coastal protection, etc.
The special requirements for construction
sites do not apply to temporary buildings erected for the
use of the construction workers, such as offices, toilets,
cloakrooms, dormitories, canteens, meeting rooms, etc. These
situations will not change as construction progresses, and
are thus subject to the general requirements of the Regulations.
The equipment used must be suitable for
the particular supply to which it is connected, and for
the duty it will meet on site. Where more than one voltage
is in use, plugs and sockets must be non interchangeable
to prevent misconnection. Six levels of voltage are recognised
for a construction site installation. They are:
1. - 25 V
single-phase SELV for portable hand-lamps in damp and confined
situations,
2. - 50
V single-phase, centre-point earthed for hand lamps
in damp and confined situations,
3. - 400 V three phase, for use
with fixed or transportable equipment with a load of more
----- than 3750 Watts,
4. - 230 V single phase, for site
buildings and fixed lighting,
5. - 110 V three phase, for transportable
equipment with a load up to 3750 Watts, and
6. - 110 V single phase, fed from
a transformer, often with an earthed centre-tapped secondary
winding, to feed transportable tools and equipment, such
as floodlighting, with a load of up to 2 kW. This supply
ensures that the voltage to earth should never exceed 55
V (see {Fig 7.5}). The primary winding of the transformer
must be RCD-protected unless the equipment fed is to be
used indoors.
Fig 7.5 Arrangement of
transformer for safety 110 V supply for a construction site
Supplies will normally be obtained
from the Electricity Supply Company. Where a site is remote,
so that a generator must be used (IT supply system) special
protective requirements apply which are beyond the scope
of this Guide, and the advice of a qualified electrical
engineer must be sought. Attention is drawn to BS 7375:
1966 Code of Practice for the distribution of electricity
on construction and building sites.